Mold Remediation Case Study

Download PDF

Teamed with Donnelly Stucco to complete a three-story winter season mold remediation project on the facility exterior.

Three Story Stucco Building Remediation

Client Situation:

  • Needed to complete a very delicate three-story remediation project without occupant disruption 
  • The building had various materials and substrate that had previous water damage 
  • Different exterior areas needed to be addressed as they were uncovered during the stucco removal and the A.E.S. forensic analysis
  • The project needed to be performed with absolutely no chance of cross-contamination or release of contaminated debris into the facility

Challenges Faced:

  • Working at high elevations and controlling the temperature in our containment to allow for our products to be applied within their specifications
  • Coordinating our work with several other trades in a seamless manner 
  • Fall protection safety equipment was needed when working outside the structure
  • Flexible scheduling of remediation in case of poor weather conditions
  • Finishing large sections of the building in a short amount of time to allow for the re-insulation and sealing of the building’s exterior

Results: 

  • Completed work with negative pressure containments as the renovation project progressed at a very aggressive pace 
  • Performed our work ahead of schedule in order to expedite the re-build
  • Protected occupants working on interior projects while completing exterior work with successful containment
  • Completed the exterior wall treatment ahead of schedule and free of problems
  • The consultant A.E.S. and Opus Construction were more than pleased with our flexibility, professionalism and our cost saving measures